Schedule
- 1st December, 2014 : Submit final draft of Conformational Switching paper to Marco
- 1st November, 2014 : Finalise results and finish first draft of Conformational Switching paper
- 15th October, 2014 : Finalise experiments
- 1st October, 2014 : Finalise conformational switching component design
- 18th September, 2014 : Return from PPSN
Todo
- Outline by 6th September
- Send container designs
- Run trials
- Mount existing container on shaker
Experiments
- Test to verify role of seed
- Components with seed
- Components without seed
- Assembly of one target structure
- Conformational switching
- Simple
- Assembly of multiple target structures
- Conformational switching
- Simple