See [[http://majorana.ulb.ac.be/wordpress/ http://majorana.ulb.ac.be/wordpress/]]
== Cluster composition ==
 
 
COMPLEX_NAME: '''athlon1400'''
 
 
- AMD Athlon 1400 (1 CPU @ 1,36GHz)
 
 
p15
 
 
 
COMPLEX_NAME: '''athlon1800'''
 
 
- AMD Athlon 1800+ (1 CPU @ 1,46GHz)
 
 
p06
 
 
 
COMPLEX_NAME: '''athlon2200'''
 
 
- AMD Athlon 2200+ (1 CPU @ 1,75GHz)
 
 
p07
 
 
 
COMPLEX_NAME: '''athlon2400'''
 
 
- AMD Athlon 2400+ (1 CPU @ 1,95GHz)
 
 
p02, p03, p04, p05, p08
 
 
 
COMPLEX_NAME: '''athlon2800'''
 
 
- AMD Athlon 2800+ (1 CPU @ 2,03GHz)
 
 
p17, p18, p19, p20, p21, p22
 
 
 
COMPLEX_NAME: '''opteron244'''
 
 
- AMD Opteron244 (2 CPU @ 1,75GHz)
 
 
r02, r03, r04, r05, r06, r07, r08, r09, r10, r11, r12, r13, r14, r15, r16, r17, r18, r19, r20, r21, r22, r23, r24, r25, r26, r27, r28, r29, r30, r31, r32, r33
 
 
 
== Queues ==
 
 
Each machine has the following 3 queues:
 
 
 
*'''<machine>.short''': max 6 jobs concurrently can run in this queue. Each job can only run for maximum '''24h of CPU time''' (so real execution of the program, without the time needed by the system for multitasking, etc). When it reaches the 24th hour it will receive a signal SIGUSR1 and after some more time a SIGKILL that will terminate it.
 
 
*'''<machine>.medium''': max 4 jobs concurrently can run in this queue, but they run at nice-level 5 (lower priority than the short ones). Each job can only run for maximum '''72h of CPU time''' (so real execution of the program, without the time needed by the system for multitasking, etc). When it reaches the 72nd hour it will receive a signal SIGUSR1 and after some more time a SIGKILL that will terminate it.
 
 
*'''<machine>.long''': only 1 job at a time can run in this queue, but it runs at nice-level 10 (lower priority than the short and the medium ones). The job can only run for maximum '''168h of CPU time''' (so real execution of the program, without the time needed by the system for multitasking, etc). When it reaches the 168th hour it will receive a signal SIGUSR1 and after some more time a SIGKILL that will terminate it.
 
 
 
YOU HAVE TO DESIGN YOUR COMPUTATIONS IN SUCH A WAY THAT THEY DON'T BLOCK A CPU FOR MORE THAN 7 DAYS IN A ROW (of CPU time)!!!!
 
 
 
== How to submit a job ==
 
 
To submit a job that lasts up to 1 day you have to specify -l COMPLEX_NAME -l shorttime in the shell script passed at the qsub command, like in this example:
 
 
#!/bin/bash
 
#$ -N name_of_the_short_job
 
#$ -l complex_name
 
#$ -l shorttime
 
#$ -cwd
 
 
 
To submit a job that lasts up to 3 days you have to specify -l COMPLEX_NAME -l mediumtime in the shell script passed at the qsub command, like in this example:
 
 
#!/bin/bash
 
#$ -N name_of_the_medium_job
 
#$ -l complex_name
 
#$ -l mediumtime
 
#$ -cwd
 
 
 
To submit a job that lasts up to 7 days you have to specify -l COMPLEX_NAME -l longtime in the shell script passed at the qsub command, like in this example:
 
 
#!/bin/bash
 
#$ -N name_of_the_long_job
 
#$ -l complex_name
 
#$ -l longtime
 
#$ -cwd
 